HANCOCK - A dispute over flood mitigation, stream maintenance and public records grew increasingly heated at the Hancock Town Council’s Sept. 1 meeting, as residents pressed officials to address what they described as preventable flood risks and delays in responding to requests for information.
During public comment, Hancock resident Sam Rowe asked the town to move ahead with limited tree and debris removal along accessible portions of Fish Creek before winter and the spring runoff season.
Rowe said recent flooding demonstrated how fallen trees and other woody debris could accumulate in waterways, obstructing or redirecting flows and creating risks for public infrastructure and private property.
He asked the board to solicit bids or quotations from qualified contractors for preventive cutting work on portions of Fish Creek that could be safely accessed and where written permission had been obtained from private landowners.
Under Rowe’s proposal, contractors would cut or break down fallen trees and other woody material that could obstruct the stream, particularly material that could contribute to a debris jam near the Bodoit Road county bridge and elsewhere. Contractors would provide hourly rates for labor and equipment, Rowe said, while the town would authorize work at individual locations.
The proposed bid specifications would require general liability insurance and workers’ compensation coverage, and work would be limited to locations approved by the town and landowners.
Rowe said he had been advised by the state Department of Environmental Conservation that the limited cutting activity he was proposing was not permitted, but urged the town to have its attorney and DEC determine whether a properly defined project could proceed.
He also cited Town Law as a potential source of authority for municipal work involving streams and watercourses, while acknowledging that such authority would not give the town automatic permission to enter private property.
Rowe asked the board to refer the proposal to the town attorney, obtain the necessary property-access agreements, adopt any required resolution and solicit bids so the work could be completed before the next major high-water event.
FOIL dispute
Rowe also challenged the town over a Freedom of Information Law request he submitted June 25 concerning floodplain work in the East Branch area.
He said he had contacted the U.S. Army Corps of Engineers and was told a federal Section 408 permit was required for the project, along with a hydraulic analysis demonstrating that the proposed work would not raise flood elevations.
Rowe said his June 25 FOIL request sought information about what action the town had taken and whether a hydraulic “no-rise” analysis had been conducted. As of the Sept. 1 meeting, he said, he had not received the records.
With Sept. 4 identified as the latest date he had been given for a response, Rowe said he was filing an appeal in advance on the grounds that the request had effectively been denied after 68 days.
He also corrected a statement he had made at an earlier meeting concerning the National Flood Insurance Program.
Rowe said he had previously stated that failure to maintain the floodplain could result in the East Branch area being removed from the federal program. He said he had since learned that the consequences could potentially extend to the entire town.
The implications of floodplain compliance, permitting and eligibility for the National Flood Insurance Program were not resolved at the meeting.
Resident demands answers
East Branch resident Brad Elmore followed Rowe during public comment, asking for a written determination regarding a matter he had formally submitted to the town Aug. 16.
Elmore said the town attorney had previously asked him to provide additional documentation. He said he had submitted the requested material and followed up with the town but had not received a response. Elmore asked that if the board chose not to answer his questions publicly, that fact be reflected in the meeting minutes.
“The public is asking questions, and they’re not being answered,” Elmore said.
Supervisor Jerry Vernold responded that the town had not been answering certain questions because of advice from its attorney.
The exchange then turned to the residents’ concerns about previous dumping, illegal allegations, and The Reporter’s coverage of the issue.
Vernold said he believed The Reporter had published statements suggesting the town had said there was “nothing that can be done” about the flooding, which he said “made the town look bad.”
Vernold clarified that while the statement that there was “nothing that can be done” was accurate, he said the town’s position was that the matter was civil and therefore outside the town’s authority to address.
Elmore disputed that characterization and said written information provided by the DEC contradicted statements previously attributed to the town.
The discussion became increasingly contentious, with Vernold eventually telling Elmore to stop the conversation.
Elmore continued to argue that town officials had failed to respond adequately to residents’ concerns and said he had incurred significant costs related to the flooding.
Vernold acknowledged that the situation had resulted in financial losses for Elmore but said the town’s position had been misrepresented, adding that it was not true that the town did not care about the impact on residents.
The exchange ended without resolving the underlying dispute over the town’s authority, its response to the flooding concerns or the status of Elmore’s requested determination.
The questions raised at the meeting now extend across several areas - stream maintenance, private-property access, state and federal permitting, floodplain management and the town’s obligations under the Freedom of Information Law.